Extension of Line 14

Fully automated since its launch in 1998, Line 14 proved to be a real success with an ever increasing number of public transport passengers, thankful for its speed and quality of service. Already extended several times, it now connects Gare Saint-Lazare to Olympiades.

The extension of line 14 is planed within the Grand Paris Express project. Northwards, the line will be extended from Gare Saint-Lazare to Saint-Denis Pleyel business hub. Southwards, the plan is to create a direct, high-frequency line between the centre of Paris to Orly airport.

Taking into account its current interconnections within Paris and the future interconnections at both of its ends, Line 14 will be connected to all of the Grand Paris Express lines (15, 16, 17 and 18), thus assuming a role of backbone for the future regional network. Moreover, it’s interconnected with some metro lines in Paris.

By 2030, Line 14 will be fully operational, with only 85-seconds intervals between trains at morning peak time in order to meet expected demand.

Realisation and commissioning will take place section by section between 2019 and 2024.

Commissioning milestones:
• 2019: Northwards section from Gare Saint-Lazare to Mairie de Saint-Ouen (a STIF/RATP project)
• 2023: Northwards section from Mairie de Saint-Ouen to Saint-Denis Pleyel
• 2023: Southwards section from Olympiades to Villejuif Institut Gustave-Roussy
• 2024: Southwards section from Villejuif Institut Gustave-Roussy to Orly

Project supervision

The extension of Line 14 will be co-supervised by STIF and RATP for the section from Gare Saint-Lazare to Mairie de Saint-Ouen. The next extensions, northwards between Mairie de Saint-Ouen and Saint-Denis Pleyel and southwards between Olympiades and Orly airport, will be supervised by Société du Grand Paris (SGP).

Ligne_14

Phase 1 – By 2019

Line 14 – Saint-Lazare / Mairie de Saint-Ouen

Grand Paris Express will kick off with the extension Line 14 from Gare Saint-Lazare to Mairie de Saint-Ouen. To be commissioned as soon as 2019, this section represents a sustainable solution to ease the existing congestion on line 13 thanks to two interconnection points, including with RER C.

The schedule for this section includes consultation, study and construction phases.

Where do we stand ?

JLL France - Grand Paris - Calendar Subway Line 14

Provisional timetable produced by STIF and RATP:
•    Public consultation: January to February 2012
•    Statement of Public Utility: October 2012
•    Construction kick-off: 2014
•    Commissioning target date: 2019-2020

Phase 2 – By 2023

Northwards Line 14 – Mairie de Saint-Ouen / Saint-Denis Pleyel

Supervised by Société du Grand Paris (SGP), this section called “Ligne 14 Nord” (Northwards Line 14) will connect Mairie de Saint-Ouen to Saint-Denis Pleyel, and will interconnect with Grand Paris Express future lines 15, 16 and 17. It is to be commissioned by 2023, approximately the same time as the future lines 16 and 17 with which it will share a section between Saint-Denis Pleyel and Le Bourget RER.

The schedule for this section includes consultation, study and construction phases.

Where do we stand ?

JLL France - Grand Paris - Calendar Subway Line 14

This section of extended Line 14 was publicly discussed by Société du Grand Paris (SGP) and the local population, from November to December 2013. These meetings aimed to present the project, engage in dialogue with inhabitants, answer their questions and take into consideration their comments.

Next steps in the timeline:
•    Public consultation: October-November 2014
•    Report from the Commission of Enquiry: February 2015

Northwards line 14, line 16 and Southwards line 17 received a favourable assessment on February 9th 2015 from the commission in charge of the public enquiry, according to the report and conclusions that were submitted to the Prefect of the Greater Paris Region and to the President of the Paris Administrative Count
•    Statement of Public Utility: 29 December 2015
•    Construction kick-off: 2016
•    Commissioning target date: by 2023

Southwards Line 14 – Olympiades / Villejuif Institut Gustave-Roussy

Supervised by Société du Grand Paris (SGP), this section called “Ligne 14 Sud” (Southwards Line 14) will connect Olympiades to Villejuif Institut Gustave-Roussy, and interconnect with Grand Paris Express future lines 14 and 15. It is to be commissioned by 2023 and will enable a direct service from Paris to the Life Sciences cluster of Villejuif – Evry.
The schedule for this section includes consultation, study and construction phases.

Where do we stand ?

JLL France - Grand Paris - Calendar Subway Line 14

Provisional timeline:
•    Public consultation: June-July 2015
The public consultation took place from June 1 to July 9, 2015. This important step i the project is to gather the public opinion on the southern segment of line 14 of the automated metro of the Grand Paris, which will be realised in two sections, including this one which will connect 4 stations from Olympiads to Villejuif IGR.
•    Report from the Commission of Enquiry of October 2015
The public Commission of enquiry presented on October 30, 2015 to the Prefect of the Greater ParisRegion, the Prefect of Paris and the President of the Administrative Tribunal of Paris, its report and conclusions concerning the southwards Line 14 of the Grand Paris Express.
The report gives a favourable opinion.
•    Statement of Public Utility: 29 July 2016

•   Construction kick-off: 2016

•    Commissioning target date: by 2023

Phase 3 – Horizon 2024

Southwards Line 14 – Villejuif Institut Gustave-Roussy / Orly airport

The section between Villejuif Institut Gustave-Roussy and Orly airport will connect with Grand Paris Express future Line 18 by 2024.

Where do we stand ? 

JLL France - Grand Paris - Calendar Subway Line 14

Provisional timeline:
•    Public consultation: June-July 2015
The public consultation took place from June 1 to July 9, 2015. This important step of the project is to gather public opinion on the southern segment of line 14 of the automated metro of the Grand Paris, which will be realised in two sections, including this part which will connect 5 stations from Villejuif Institut Gustave-Roussy to Orly airport.
•    Report from the Commission of Enquiry of October 2015
The public Commission of enquiry presented on October 30, 2015 to the Prefect of the Greater ParisRegion, the Prefect of Paris and the President of the Administrative Tribunal of Paris, its report and conclusions motivated on the southwards Line 14 of the Grand Paris Express.The report gives a favorable opinion.
•    Statement of Public Utility: 29 July 2016

•    Construction kick-off: 2016

•    Commissioning target date: by 2024 (3 years before the initial target date)